logo
    • Buy Crypto
    • Markets
    • Futures
    • Spot
    • Earn
    • Affiliates & AI
    • More
    1. WEEX
    2. Crypto News
    3. Oracle's $165 Billion Data Center Project Delayed by Gas Pipeline

    Oracle's $165 Billion Data Center Project Delayed by Gas Pipeline

    By: www.tokenpost.kr|2026/08/14 19:52:53
    0
    Share
    copy
    Prefer us on GooglePrefer us on Google
    GASGAS
    00.00%--
    REQREQ
    00.00%--
    FuelFuel
    NOTNOT
     

    Oracle's AI data center project in New Mexico has been delayed due to the schedule of a natural gas pipeline. The Project Jupiter, estimated to be worth up to $165 billion (approximately 234 trillion won), highlights that infrastructure projects require coordination of power, gas, water, and permits before server installation can begin.

    Oilprice reported on the 14th (local time) that Energy Transfer's subsidiary, Transwestern Pipeline, has postponed the expected operational date of the Green Chile Project from August 15, 2026, to February 1, 2027. This pipeline is the infrastructure that supplies natural gas to Project Jupiter in Dona Ana County, New Mexico.

    Project Jupiter is an AI data center campus being developed by Oracle and BorderPlex Digital Assets. Public FERC documents indicate that this project is linked to an investment of up to $165 billion, over 4,000 construction jobs, and 1,500 permanent jobs.

    In a statement on April 27, Oracle announced that Bloom Energy's fuel cells would be used as on-site power facilities. At that time, Oracle and Bloom Energy announced an expansion of fuel cell supply of up to 2.8 GW, proposing to convert existing gas turbine and diesel generator designs into fuel cell microgrids.

    The bottleneck is not the fuel cells themselves but the fuel supply chain. Data Center Dynamics reported that the Green Chile Project is designed to supply up to 400,000 Dth, approximately 400 million cubic feet, of natural gas to the site daily. Although fuel cells do not operate on combustion, the current plans assume the supply of natural gas and pipeline permits.

    The Green Chile Project is part of a solution for on-site power generation as the power demand of data centers becomes difficult to manage solely through existing power grid connections. While having the data center's own or adjacent power facilities can reduce transmission bottlenecks, it is challenging to avoid separate regulatory processes related to fuel procurement, air quality permits, and land crossing rights.

    The New Mexico State Land Office announced on July 15 that it had again denied Energy Transfer's request for reconsideration. The application concerned a 0.6-mile section of the 17-mile pipeline that crosses state land.

    Stephanie Garcia Richard, the New Mexico Land Commissioner, stated in a press release that "large-scale AI data centers can rapidly deplete essential natural resources like water and generate high emissions in the process of securing operational power." The state land office cited concerns over water resource burdens, greenhouse gas emissions, and compliance with the interests of state trust lands as reasons for the denial.

    Oracle emphasizes the local economic impact of the project. In a statement on July 28, the company noted that Project Jupiter has already generated approximately $80 million (about 113.4 billion won) in state and county tax revenue, with long-term economic effects potentially exceeding $4.7 billion (approximately 6.6646 trillion won).

    However, Oracle noted at the end of the same announcement that projections regarding tax revenue, employment, and investment are contingent upon air permits and pipeline approvals. This creates a scenario where the company's economic impact claims clash with the state government's environmental and land management assessments within the same permitting process.

    Power design plans are also undergoing public review. Oracle announced on June 3 that the New Mexico Environment Department had moved the revised air quality permit application to the public review stage. The company explained that the new design would reduce nitrogen oxide emissions by approximately 92% compared to the existing gas turbine plans and would not use drinking water sources for cooling and power generation.

    OpenAI has also been mentioned as a background partner in Project Jupiter. As the demand for AI model training and inference grows, data centers are evolving into businesses that encompass not only servers and semiconductors but also power procurement methods, cooling water usage, local tax revenue, and land use issues.

    Market reactions have been limited, but interest in related stocks has emerged. Stocktwits reported that following the state land office's re-denial on July 15, the volume of messages related to Oracle and Bloom Energy doubled within 24 hours. However, this reflects a community trading platform's response and does not imply that changes in project schedules will determine stock price directions.

    For domestic investors, this issue illustrates that investments in AI infrastructure are not solely about semiconductors and cloud contracts. Earlier reports indicated that the share of data centers in the backlog of Texas power grid connections has increased. The U.S. data center business is transitioning to a structure where power grid access, on-site generation, gas procurement, and local government permits simultaneously influence pricing and schedules.

    This situation demonstrates that even if the expansion of AI data centers shifts to on-site generation outside the power grid, it is challenging to avoid permitting risks. The schedule impact of Project Jupiter will depend on the operational goals of the Green Chile Project set for February 1, 2027, and the results of the revised power plan review.

    -- Price

    --
    --
    --

    This content is provided for general informational purposes only and doesn't constitute financial, investment, legal, or tax advice. Any events, rewards, online promotions, or related information mentioned herein should not be considered a recommendation, solicitation, or invitation to purchase, sell, trade, or otherwise deal in any crypto assets. Crypto assets are highly volatile and may result in loss. The availability of WEEX services, products, and related events may vary by region. You are responsible for ensuring that your participation is in accordance with applicable local laws and regulations.

    You may also like

    Kinetiq Launches Hyperliquid L2 Network Elysium, HYPE as Native Gas Token

    Kinetiq Launches Hyperliquid L2 Network Elysium, HYPE as Native Gas Token

    6GW Nuclear Power Supply Agreement: Non-Binding Framework with Nano Nuclear and Tillman

    6GW Nuclear Power Supply Agreement: Non-Binding Framework with Nano Nuclear and Tillman

    Nano Nuclear Energy (NANO Nuclear Energy·$NNE) has entered into a non-binding commercial framework with Tillman affiliates to explore a power supply plan for micro-reactors exceeding 6GW in the U.S. AI industrial zone.
    Kinetiq Launches Elysium L2 Network to Enhance Hyperliquid Performance

    Kinetiq Launches Elysium L2 Network to Enhance Hyperliquid Performance

    Shein Debuts on the Hong Kong Stock Exchange, Aiming to Raise Over $1.7 Billion

    Shein Debuts on the Hong Kong Stock Exchange, Aiming to Raise Over $1.7 Billion

    The company reaches a valuation of $26.8 billion, a figure lower than in 2022. It plans to use the funds to finance its technological capabilities and strengthen its international presence. Criticism.
    Norway to Continue Oil and Gas Production in the Arctic, Ignoring EU Position

    Norway to Continue Oil and Gas Production in the Arctic, Ignoring EU Position

    Can x402 Micro-Payments Save the Content Internet from Being Squeezed?

    Can x402 Micro-Payments Save the Content Internet from Being Squeezed?

    Japan's Electricity Price Hits 25.18 Yen, Highest Record of 2023

    Japan's Electricity Price Hits 25.18 Yen, Highest Record of 2023

    The wholesale electricity price for the next day across Japan has risen to 25.18 yen/kWh, marking the highest level since January 2023. The increase is due to a surge in cooling demand from the heatwave and rising liquefied natural gas (LNG) prices.
    HyperEVM Records Daily Fees of $538,100

    HyperEVM Records Daily Fees of $538,100

    HyperEVM, the Ethereum Virtual Machine-compatible execution environment of the HyperLiquid (HYPE) ecosystem, recorded a daily fee revenue of $538,100 (approximately 74.5 million KRW) on August 23.
    Iran Discovers 7.5 Trillion Cubic Feet of Natural Gas

    Iran Discovers 7.5 Trillion Cubic Feet of Natural Gas

    India Increases Russian Oil Imports to Record 2.6 Million Barrels per Day

    India Increases Russian Oil Imports to Record 2.6 Million Barrels per Day

    Oil Prices on August 24: Brent Falls by $1.23

    Oil Prices on August 24: Brent Falls by $1.23

    Putin Shifts Responsibility for Fuel Crisis to Government

    Putin Shifts Responsibility for Fuel Crisis to Government

    Wall Street Morning Briefing: Iran Sanctions Details to be Announced Tonight, Nvidia Server Prices Expected to Rise, Tesla Surges Over 5% Leading the Seven Giants

    Wall Street Morning Briefing: Iran Sanctions Details to be Announced Tonight, Nvidia Server Prices Expected to Rise, Tesla Surges Over 5% Leading the Seven Giants

    Polygon Advances Staking and Tokenomics Reform, POL Staking Yields Expected to Double

    Polygon Advances Staking and Tokenomics Reform, POL Staking Yields Expected to Double

    Iran Advances Possibility of Imposing Transit Fees in Hormuz Strait

    Iran Advances Possibility of Imposing Transit Fees in Hormuz Strait

    Iran's parliament has progressed to the final approval stage for a provision that would allow the imposition of transit fees on vessels passing through the Strait of Hormuz. The issue of transit fees has resurfaced in negotiations between Iran and Oman regarding this critical route for energy and ma...
    The US approved high-leverage Bitcoin trading while crypto founders remain legally blocked from raising funds

    The US approved high-leverage Bitcoin trading while crypto founders remain legally blocked from raising funds

    Bitcoin perpetual futures are now live on regulated US exchanges, while the SEC’s proposed crypto fundraising rules remain months from a final vote.
    U.S. Diesel Crack Spread Surpasses $100, Impact of Russian Refinery Supply Disruptions

    U.S. Diesel Crack Spread Surpasses $100, Impact of Russian Refinery Supply Disruptions

    The U.S. diesel crack spread has risen to around $100 per barrel, further highlighting the bottlenecks in the refined oil market. The refining margin for producing diesel has outpaced crude oil prices.
    Qatar Reports Q1 Deficit of 10.3 Billion Riyals, Impact of LNG Export Disruptions

    Qatar Reports Q1 Deficit of 10.3 Billion Riyals, Impact of LNG Export Disruptions

    Qatar's fiscal balance recorded a deficit of 10.3 billion riyals in the first quarter of this year. Following the US-Iran conflict, disruptions in liquefied natural gas (LNG) exports have increased, highlighting the vulnerabilities of the energy-dependent Gulf economy.
    200 MAHA Activists Urge Trump to Oppose Increased Coal Use for AI Data Centers

    200 MAHA Activists Urge Trump to Oppose Increased Coal Use for AI Data Centers

    Approximately 200 activists from the MAHA (Make America Healthy Again) movement have demanded that U.S. President Donald Trump not increase coal usage due to the power demands of artificial intelligence (AI) data centers.
    Base Plans to Incorporate Ethereum EIP-8130 Draft in September

    Base Plans to Incorporate Ethereum EIP-8130 Draft in September

    Discussions surrounding EIP-8130, aimed at restructuring wallet account standards in the Ethereum (ETH) ecosystem, are gaining prominence alongside Base's Cobalt upgrade plans. The core focus is on wallet ...
    France and Saudi Arabia to Discuss Alternative Routes to Hormuz on 24th

    France and Saudi Arabia to Discuss Alternative Routes to Hormuz on 24th

    French President Emmanuel Macron and Saudi Crown Prince Mohammed bin Salman will discuss alternative routes to the Strait of Hormuz and bilateral agreements on the 24th.
    Suspect in Nord Stream Explosion Arrested in Croatia

    Suspect in Nord Stream Explosion Arrested in Croatia

    A Ukrainian national suspect in the Nord Stream 1 and 2 gas pipeline explosions was arrested in Croatia on August 19, 2026. The German investigation has made progress, raising tensions between Berlin and Kyiv.
    Utorg Launches iPhone App, Official Channel Statements Diverge

    Utorg Launches iPhone App, Official Channel Statements Diverge

    Utorg has announced the launch of its consumer app for iPhone, named Utapp, but the service descriptions on its official site and terms of service are still inconsistent. The app is said to bundle self-custody wallets, cards, and gasless swap features, but the wording surrounding the actual offering...
    Trezor Begins Supporting HyperEVM HYPE

    Trezor Begins Supporting HyperEVM HYPE

    Trezor's addition of HyperEVM support has expanded the range of managing HYPE and HyperEVM ecosystem assets based on hardware wallets.
    Walmart Accepts Apple Pay After Years of Resistance

    Walmart Accepts Apple Pay After Years of Resistance

    October Push for Compute Futures, Limited Hedging for Miners

    October Push for Compute Futures, Limited Hedging for Miners

    As Bitcoin (BTC) mining companies expand into AI infrastructure, analyses suggest that the newly proposed compute derivatives may not fully mitigate their core risks.
    Russia Destroys Over 300 Ukrainian Gas Stations in Six Months

    Russia Destroys Over 300 Ukrainian Gas Stations in Six Months

    ArkStream Capital: From AI Drain to RWA Rise, Capital Migration in the Crypto Market by 2026

    ArkStream Capital: From AI Drain to RWA Rise, Capital Migration in the Crypto Market by 2026

    Nigeria Announces Plan to Attract Up to $50 Billion in Deepwater Oil and Gas Investments by 2030

    Nigeria Announces Plan to Attract Up to $50 Billion in Deepwater Oil and Gas Investments by 2030

    Nigeria has unveiled a new regulatory framework to attract up to $50 billion (approximately 69.75 trillion won) in deepwater oil and gas investments by 2030. The approach reduces the need for individual project negotiations.
    Ukraine Accumulates 14.3 Billion Cubic Meters of Gas for Heating Season

    Ukraine Accumulates 14.3 Billion Cubic Meters of Gas for Heating Season

    Kinetiq Launches Hyperliquid L2 Network Elysium, HYPE as Native Gas Token

    6GW Nuclear Power Supply Agreement: Non-Binding Framework with Nano Nuclear and Tillman

    Nano Nuclear Energy (NANO Nuclear Energy·$NNE) has entered into a non-binding commercial framework with Tillman affiliates to explore a power supply plan for micro-reactors exceeding 6GW in the U.S. AI industrial zone.

    Kinetiq Launches Elysium L2 Network to Enhance Hyperliquid Performance

    Shein Debuts on the Hong Kong Stock Exchange, Aiming to Raise Over $1.7 Billion

    The company reaches a valuation of $26.8 billion, a figure lower than in 2022. It plans to use the funds to finance its technological capabilities and strengthen its international presence. Criticism.

    Norway to Continue Oil and Gas Production in the Arctic, Ignoring EU Position

    Can x402 Micro-Payments Save the Content Internet from Being Squeezed?

    ...
    100,000 USDT in rewards awaits
    Trade stock tokens with 0 fees—get 10 USDT on your first trade
    100,000 USDT in rewards awaitsUnlock up to 800 USDT

    Contents

    gas

    Latest articles

    08/24/2026

    6GW Nuclear Power Supply Agreement: Non-Binding Framework with Nano Nuclear and Tillman

    Nano Nuclear Energy (NANO Nuclear Energy·$NNE) has entered into a non-binding commercial framework with Tillman affiliates to explore a power supply plan for micro-reactors exceeding 6GW in the U.S. AI industrial zone.
    GASGAS
    00.00%--
    XNOXNO
    00.00%--
    08/24/2026

    Shein Debuts on the Hong Kong Stock Exchange, Aiming to Raise Over $1.7 Billion

    The company reaches a valuation of $26.8 billion, a figure lower than in 2022. It plans to use the funds to finance its technological capabilities and strengthen its international presence. Criticism.
    GASGAS
    00.00%--
    08/24/2026

    Can x402 Micro-Payments Save the Content Internet from Being Squeezed?

    JSTJST
    00.00%--
    SNTSNT
    00.00%--
    GASGAS
    00.00%--
    MEMEMEME
    00.00%--
    08/24/2026

    Wall Street Morning Briefing: Iran Sanctions Details to be Announced Tonight, Nvidia Server Prices Expected to Rise, Tesla Surges Over 5% Leading the Seven Giants

    FLOWFLOW
    00.00%--
    ONEONE
    00.00%--
    GASGAS
    00.00%--
    08/23/2026

    The US approved high-leverage Bitcoin trading while crypto founders remain legally blocked from raising funds

    Bitcoin perpetual futures are now live on regulated US exchanges, while the SEC’s proposed crypto fundraising rules remain months from a final vote.
    USUALUSUAL
    00.00%--
    JSTJST
    00.00%--
    SNTSNT
    00.00%--
    GASGAS
    00.00%--
    More

    Latest coin listings on WEEX

    logoCommunity
    iconiconiconiconiconiconicon
    Customer Support:@weikecs
    Business Cooperation:@weikecs
    Quant Trading & MM:bd@weex.com
    VIP Program:support@weex.com
    • About Us
    • Announcement Center
    • Media Kit
    • WEEX Community
    • WXT Zone
    • Announcement
    • Legal Statement
    • Risk Disclosure
    • Terms and Policies
    • Privacy Policy
    • Whistleblower Notice
    • AML/CTF Policy
    • Law Enforcement
    • User Guide
    • Product Launches
    • Crypto News
    • Product Launches
    • Crypto Wiki
    • Learn
    • Q&A
    • Spot
    • Futures
    • Glossary
    • VIP Program
    • Download
    • Affiliate
    • Protection Fund
    • Proof of Reserves
    • Sitemap
    • ETFs
    • Crypto Prices
    • Price Predictions
    • WXT Price
    • BTC Price
    • ETH Price
    • DOGE Price
    • How to Buy Crypto
    • How to Buy WXT
    • How to Buy BTC
    • How to Buy ETH
    • How to Buy DOGE
    • Help Center
    • Fee Schedule
    • Trading Rules
    • WEEX Academy
    • Contact Verifier
    • Submit Feedback
    • About Us
    • Announcement Center
    • Media Kit
    • WEEX Community
    • WXT Zone
    • Announcement
    • Help Center
    • Fee Schedule
    • Trading Rules
    • WEEX Academy
    • Contact Verifier
    • Submit Feedback
    • Customer Support Bot
    • VIP Services
    • Legal Statement
    • Risk Disclosure
    • Terms and Policies
    • Privacy Policy
    • Whistleblower Notice
    • AML/CTF Policy
    • Law Enforcement
    • Proof of Reserves
    • Invite Friends
    • OTC
    • Download
    • Affiliate
    • VIP Program
    • API
    • Broker
    • Listing Application
    • Affiliate T&C
    • Sitemap
    • Futures
    • Spot
    • Copy Trade
    • Markets
    • WEEX Store
    • User Guide
    • Product Launches
    • Crypto News
    • Product Launches
    • Crypto Wiki
    • Learn
    • Q&A
    • Spot
    • Futures
    • Glossary
    • VIP Program
    • Download
    • Affiliate
    • Protection Fund
    • Proof of Reserves
    • Sitemap
    • ETFs
    • Crypto Prices
    • Price Predictions
    • WXT Price
    • BTC Price
    • ETH Price
    • DOGE Price
    • How to Buy Crypto
    • How to Buy WXT
    • How to Buy BTC
    • How to Buy ETH
    • How to Buy DOGE
    • About Us
    • Announcement Center
    • Media Kit
    • WEEX Community
    • WXT Zone
    • Announcement
    • Help Center
    • Fee Schedule
    • Trading Rules
    • WEEX Academy
    • Contact Verifier
    • Submit Feedback
    • Legal Statement
    • Risk Disclosure
    • Terms and Policies
    • Privacy Policy
    • Whistleblower Notice
    • AML/CTF Policy
    • Law Enforcement
    • Customer Support Bot
    • VIP Services
    • Futures
    • Spot
    • Copy Trade
    • Markets
    • WEEX Store
    • Proof of Reserves
    • Invite Friends
    • OTC
    • Download
    • Affiliate
    • VIP Program
    • API
    • Broker
    • Listing Application
    • Affiliate T&C
    • Sitemap
    • User Guide
    • Product Launches
    • Crypto News
    • Product Launches
    • Crypto Wiki
    • Learn
    • Q&A
    • Spot
    • Futures
    • Glossary
    • VIP Program
    • Download
    • Affiliate
    • Protection Fund
    • Proof of Reserves
    • Sitemap
    • ETFs
    • Crypto Prices
    • Price Predictions
    • WXT Price
    • BTC Price
    • ETH Price
    • DOGE Price
    • How to Buy Crypto
    • How to Buy WXT
    • How to Buy BTC
    • How to Buy ETH
    • How to Buy DOGE

    Where new wealth is made

    Download app

    Sign Up
    h5 logo
    Download